Elektrociepłownia Białystok completed the implementation of an investment related with the combustion of biomass generation unit with Heat Accumulation System. The project was aimed at reducing the emission of harmful substances into the atmosphere, thus increasing the security of supply of heat. This is another step of the Company to increase the production of electricity from renewable energy sources. The opening ceremony took place on 18 April this year.
Elektrociepłowna Białystok has started another project in August 2013 - construction of the heat recovery from the exhaust of the biomass boiler. Its task is to recover and use heat that is now lost. The maximum boiler capacity will amount to 18.4 MW. This is the first of its kind investment in Poland, and the value of its implementation is PLN 25.5 million. Consortium Mostostal Warszawa and Radscan Intervex Polska is responsible for the construction. Accomplishment of the project is planned for the fourth quarter of 2014.